Skip to main content

mmup civil questions 01

CIVIL QUESTIONS 


Pick up the correct statement from the following:
Pick up the correct statement from the following:
The theory of formation of concrete is based on the phenomena of formation of voids
The bulking of sand is taken into account while volumetric proportioning of the aggregates
The dry sand and the sand completely flooded with water, have practically the same volume
The expansion and contraction joints are provided if concrete structures exceed 12 m in length
All the above

Answer: Option E
Initial setting time of cement for asbestos cement products should be not less than
30 minutes
50 minutes
75 minutes
90 minutes
Answer: Option D
Pick up the correct statement regarding low heat cement from the following:
It possesses less compressive strength
Its initial setting time is about one hour
Its final setting time is about 10 hours
Its mainly used for mass concrete work
All the above.
Answer: Option E
Name the type of cement from the following for canal linings :
sulphate resisting cement
rapid hardening cement
quick setting cement
pozzuolana cement.
Answer: Option A

If water required for 1 bag of cement is 30 litres, the water cement ratio is :
0.40
0.50
0.60
None of these.
Answer: Option C
The weight of 1 m3 of brick earth, is about
1200 kg
1500 kg
1800 kg
2000 kg.
Answer: Option C


Mastic asphalt is normally used for
sound insulation
water proofing
fire proofing
none to these.
Answer: Option B
Strength of cement concrete primarily depends upon
quality of water
quantity of aggregate
quantity of cement
water-cement ratio.
Answer: Option D
Soundness of cement is tested by
Vicat's apparatus
Le-chatelier apparatus
compressive strength testing apparatus
none of the these.
Answer: Option B
Slump test for concrete is carried out, to determine
strength
durability
workability
water content.
Answer: Option C
In case of Raymond pile
lengths vary from 6 m to 12 m
diameter of top of piles varies from 40 cm to 60 cm
diameter of pile at bottom varies from 20 cm to 28 cm
thickness of outer shell depends upon pile diameter
all the above.
Answer: Option E
The foundations are placed below ground level, to increase
strength
workability
stability of structure
all the above.
Answer: Option C

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than
the column spacing
one-third the column spacing
half the column spacing
three-fourth the column spacing
none of these.
Answer: Option B
The concrete slump recommended for beams and slabs ; is
25 to 50 mm
25 to 75 mm
30 to 125 mm
50 to 100 mm
none of these.
Answer: Option C

The entrained concrete is used in lining walls and roofs for making
heat insulated
sound insulated
neither (a) nor (b)
both (a) and (b).
Answer: Option D
For providing a raft foundation, the following activities are involved
  1. ramming the foundation bed
  2. excavation of the soil upto required depth
  3. laying the reinforcement over the foundation bed
  4. curing the cement concrete placed over reinforcement
  5. pouring the cement concrete over the reinforcement.

The correct sequence is
1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4
3, 2, 5, 1, 4.
Answer: Option C
During percussion drilling
ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole
caving or mixing of strata are caused in soft soils or cohesionless soils
the soil to a considerable depth below the bottom of the hole gets disturbed
all the above.
Answer: Option D
Raft foundation are generally preferred to when the area required for individual footing, is more than
25% to total area
30% of total area
40% to total area
50% of total area.
Answer: Option D
Pick up the incorrect statement from the following:
The retaining wall should be structurally capable to resist the applied earth pressure
The section of the retaining wall should be so proportioned that it may not overturn by the lateral pressure
The retaining wall should be safe against sliding
The foundation of the retaining wall should not be stressed beyond safe bearing capacity ; due to its weight and the force resulting from the earth pressure
to drain off water from the earth retained, weep holes are provided near the top of the retaining wall.
Answer: Option E
The process of keeping concrete moist for a certain period after its finishing, is known as
finishing of concrete
curing of concrete
placing of concrete
compaction of concrete
none of these.
Answer: Option B
Raft foundations are used for :
providing increased area of foundation over poor bearing capacity of soil
spanning over small soft or loose pockets
counter acting the hydrostatic effect
all the above.
Answer: Option D
The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as
combined footing
strap footing
raft footing
none of these
Answer: Option C

For a wall carrying heavy load on low bearing capacity soil,
lean concrete bed is provided
thick concrete bed is provided
reinforced concrete bed is provided
(a) and (c) of the above
(b) and (c) of the above.
Answer: Option D
The bearing capacity of a water logged soil, may be improved by
grouting
chemical action
drainage
compaction.
Answer: Option C
Two columns 50 cm x 50 cm and 60 cm x 60 cm carry 80 tonnes and 120 tonnes of loads respectively. The centre to centre distance between columns is 5.00 metres. The permissible bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following:
distance of C.G. of the loads from the smaller column = 3.00 m
the length of the foundation slab = 7.00 m
area of footing slab = 11.00 m2
width of the footing = 1.57 m.
all the above.
Answer: Option E

The formWork including the props can be removed from beams, only after
3 day
7 days
14 days
21 days.
Answer: Option C
The concrete slump recommended for foundations, is
25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm
none of these.
Answer: Option C


The construction joints in buildings are provided after
10 m
15 m
20 m
40 m
60 m.
Answer: Option D
Pick up the correct statements from the following :
cracks appear on the plastered surface in the form of hair cracks
in brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
excessive thermal variations in the backing or plaster causes the plaster to fall
all the above.
Answer: Option D
Pick up the correct statement from the following:
Plain cement concrete is equally strong in compression as well as in tension
Slump test is performed to check concrete strength
Curing of concrete is done for proper compaction of cement
Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates
Concrete is a mixture of binding material, coarse aggregate and water.
Answer: Option D

Pick up the correct statement from the following :
Isolated footing is provided under column to transfer the load safely to soil bed
column footings may have steps or projections in the concrete base
heavily loaded column base must be provided steel reinforcement in both directions
the concrete offset should be at least 15 cm on all sides
all the above.
Answer: Option E
If h is the difference in level between end points separated by l, then the slope correction is . The second term may be neglected if the value of h in a 20 m distance is less than
m
1 m
2 m
3 m
Answer: Option D


The accuracy of measurement in chain surveying, does not depend upon
length of the offset
scale of the plotting
importance of the features
general layout of the chain lines.
Answer: Option D
Offsets are measured with an accuracy of 1 in 40. If the point on the paper from both sources of error (due to angular and measurement errors) is not to exceed 0.05 cm on a scale of 1 cm = 20 m, the maximum length of offset should be limited to
14.14
28.28 m
200 m
none of these.
Answer: Option B
Ranging in chain survey means
looking at an isolated point not on the line
establishing an intermediate point on the line
determining the distance between end points
determining the offset distance
none of these
Answer: Option B

The operation of resection involves the following steps
  1. rough orientation of the plane table
  2. the three lines form a triangle of error
  3. drawing lines back through the three control points
  4. select a point in the triangle of error such that each ray is equally rotated either clockwise or anti clockwise
  5. the points obtained by three rays is the correct location.
    The correct sequence is
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 4, 3, 2, 5
1, 3, 2, 4, 5
Answer: Option A
If the length of a transition curve to be introduced between a straight and a circular curve of radius 500 m is 90 m, the maximum perpendicular offset for the transition curve, is
0.70 m
1.70 m
2.70 m
3.70 m
4.70 m
Answer: Option C
For quality control of Portland cement, the test essentially done is
setting time
soundness
tensile strength
consistency
all the above.
Answer: Option E
If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is,
20%
25%
30%
35%
40%


Answer: Option B
Hydration of cement is due to chemical action of water with
Tricalcium silicate and dicalcium silicate
Dicalcium silicate and tricalcium aluminate
Tricalcium aluminate and tricalcium alumino ferrite
All the above.
Answer: Option D
Curing
reduces the shrinkage of concrete
preserves the properties of concrete
prevents the loss of water by evaporation
all of the above.
Answer: Option D
Curing a concrete for long period ensures better
volume stability
strength
water resistance
water tightness and durability
all the above.
Answer: Option E
Pick up the correct statement from the following:
Insufficient quantity of water makes the concrete mix harsh
Insufficient quantity of water makes the concrete unworkable
Excess quantity of water makes the concrete segregated
Excess quantity of water causes bleeding in concrete
All the above
Answer: Option E
Workability of concrete is measured by
Vicat apparatus test
Slump test
Minimum void method
Talbot Richard test.
Answer: Option B
Shrinkage in concrete can be reduced by using
low water cement ratio
less cement in the concrete
proper concrete mix
presaturated aggregates
all the above.
Answer: Option E
A construction joint is provided where
bending moment is small
shear force is small
the member is supported by other member
all the above.
Answer: Option D
Pick up the correct statement from the following:
According to the petrological characteristics, concrete aggregates are classified as heavy weight, normal weight and light weight
According to the shape of the particles, concrete aggregates are classified as rounded irregular, angular and flaky
According to the surface texture of the particles, the concrete aggregates are classified as glassy, smooth, granular, rough, crystalline, honey combed and porous
All the above.
Answer: Option D

Pick up the incorrect statement from the following:
The degree of grinding of cement, is called fineness
The process of changing cement paste into hard mass, is known as setting of cement
The phenomenon by virtue of which cement does not allow transmission of sound, is known as soundness of cement
The heat generated during chemical reaction of cement with water, is known as heat of hydration
None of these.
Answer: Option C

Permissible compressive strength of M 150 concrete grade is
100 kg/cm2
150 kg/cm2
200 kg/cm2
250 kg/cm2
300 kg/cm2
Answer: Option C
Slump test of concrete is a measure ofits
consistency
compressive strength
tensile strength
impact value.
Answer: Option A
Water cement ratio is
volume of water to that of cement
weight of water to that of cement
weight of concrete to that of water
volume of concrete to that of water
both (a) and (b) of the above.
Answer: Option E
Separation of water or water sand cement from a freshly concrete, is known
bleeding
creeping
segregation
flooding
none of these.
Answer: Option A
According to Water-Cement Ratio Law, the strength of workable plastic concrete
depends upon the amount of water used in the mix
does not depend upon the quality of cement mixed with aggregates
does not depend upon the quanity of cement mixed with aggregates
all the above
Answer: Option D
High temperature
increases the strength of concrete
decreases the strength of concrete
has no effect on the strength of concrete
none of these.
Answer: Option B
Allowable shear strength of concrete, depends upon
shear strength
tensile strength
compressive strength
none of these.
Answer: Option A
Workability of concrete mix with low water cement ratio is determined by
tensile strength test
slump test
compaction factor test
flexural strength test
none of these
Answer: Option C
While designing an air entrained concrete
water cement ratio is reduced
proportion of aggregates is reduced
an allowance for the entrained air is made
strength of the concrete, is reduced
all the above
Answer: Option E
Concrete gains strength due to
chemical reaction of cement with sand and coarse aggregates
evaporation of water from concrete
hydration of cement
All the above.
Answer: Option C
Expansion joints are provided if the length of concrete structures exceeds
10 m
15 m
15 m
35 m
45 m
Answer: Option E
Workability improved by adding
fly ash
hydrated lime
calcium chloride
bentonite
all the above.
Answer: Option E

If the slump of a concrete mix is 60 mm, its workability is
very low
low
medium
high
none of these.
Answer: Option C
Pick up the correct statement from the following:
Construction joints in columns are provided a few cm below the junction of beam
Construction joints in columns are provided at the bottom haunching
Construction joints in beams and slabs are provided within middel third
Constructionjoints are generally provided in positions subjected to least shear force
All the above.
Answer: Option E
The shortest distance between two places measured along the surface of the earth, is
length of the equator between their longitudes
length of the parallel between their longitudes
length of the arc of the great circle passing through them
none of these.
Answer: Option C
In the cantilever truss as shown in below figure, the horizontal component of the reaction at A, is
30 tonnes
60 tonnes
90 tonnes
120 tonnes
150 tonnes.
Answer: Option A
For a simply supported beam with a central load, the bending moment is
least at the centre
least at the supports
maximum at the supports
maximum at the centre.
Answer: Option D

A simply supported beam carrying a uniformly distributed load over its whole span, is propped at the centre of the span so that the beam is held to the level of the end supports. The reaction of the prop will be
half the distributed load
3/8th the distributed load
5/8th the distributed load
distributed load.
none of these.
Answer: Option C

The range within which a load can be applied on a rectangular column, to avoid any tensile stress, is
one-half of the base
one-fifth of the base
one-fourth of the base
one-fifth of the base
one sixth of the base on either side of centroid.
Answer: Option B
The shear stress at any section of a shaft is maximum
at the centre of the section
at a distance r/2 from the centre
at the top of the surface
at a distance 3/4 r from the centre
none of these.
Answer: Option C
The region of the cross-section of a column in which compressive load may be applied without producing any tensile stress, is known as the core of the cross-section. In circular columns the radius of the core, is
one-half of the radius
one-third of the radius
one-quarter of the radius
one-fifth of the radius
one-sixth of the radius.
Answer: Option C
The maximum bending moment due to a moving load on a simply supported beam, occurs
at the mid span
at the supports
under the load
anywhere on the beam
none of these.
Answer: Option C

A simply supported beam of span L carries a uniformly distributed load W. The maximum bending moment M is
Answer: Option C
A cantilever beam rectangular in cross-section is subjected to an isolated load at its free end. If the width of the beam is doubled, the deflection of the free end will be changed in the ratio of
8
1/8
1/2
2
3


Answer: Option C
When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is called
shear stress
compressive stress
tensile stress
transverse stress
Answer: Option C
Stress in a beam due to simple bending, is
directly proportional
inversely proportional
curvilinearly related
none of these.
Answer: Option A
The bending moment is maximum on a section where shearing force
is maximum
is minimum
is equal
changes sign.
Answer: Option D


A district road with a bituminous pavement has a horizontal curve of 1000 m for a design speed of 75 km ph. The super-elevation is
1 in 40
1 in 50
1 in 60
1 in 70
none of these.
Answer: Option A
The total length of a valley formed by two gradients - 3% and + 2% curve between the two tangent points to provide a rate of change of centrifugal acceleration 0.6 m/sec2, for a design speed 100 km ph, is
16.0 m
42.3 m
84.6 m
none of these
Answer: Option A
The advantage of providing superelevation on roads, is
higher speed of vehicles
increased volume of traffic
reduced maintenance cost of the roads
draining off rain water quickly
all the above.
Answer: Option E
For a vehicle moving with a speed of 80 km per hour, the brake reaction time, in ordinary cases, is
1 sec
1.5 sec
2.0 sec
2.5 sec
3.0 sec
Answer: Option D


eory of formation of concrete is based on the phenomena of formation of voids
The bulking of sand is taken into account while volumetric proportioning of the aggregates
The dry sand and the sand completely flooded with water, have practically the same volume
The expansion and contraction joints are provided if concrete structures exceed 12 m in length
All the above

Answer: Option E
Initial setting time of cement for asbestos cement products should be not less than
30 minutes
50 minutes
75 minutes
90 minutes
Answer: Option D
Pick up the correct statement regarding low heat cement from the following:
It possesses less compressive strength
Its initial setting time is about one hour
Its final setting time is about 10 hours
Its mainly used for mass concrete work
All the above.
Answer: Option E
Name the type of cement from the following for canal linings :
sulphate resisting cement
rapid hardening cement
quick setting cement
pozzuolana cement.
Answer: Option A

If water required for 1 bag of cement is 30 litres, the water cement ratio is :
0.40
0.50
0.60
None of these.

Answer: Option C
The weight of 1 m3 of brick earth, is about
1200 kg
1500 kg
1800 kg
2000 kg.

Answer: Option C


Mastic asphalt is normally used for
sound insulation
water proofing
fire proofing
none to these.
Answer: Option B
Strength of cement concrete primarily depends upon
quality of water
quantity of aggregate
quantity of cement
water-cement ratio.
Answer: Option D
Soundness of cement is tested by
Vicat's apparatus
Le-chatelier apparatus
compressive strength testing apparatus
none of the these.
Answer: Option B
Slump test for concrete is carried out, to determine
strength
durability
workability
water content.
Answer: Option C
In case of Raymond pile
lengths vary from 6 m to 12 m
diameter of top of piles varies from 40 cm to 60 cm
diameter of pile at bottom varies from 20 cm to 28 cm
thickness of outer shell depends upon pile diameter
all the above.
Answer: Option E
The foundations are placed below ground level, to increase
strength
workability
stability of structure
all the above.
Answer: Option C

The loose pockets in soil mass can be bridged safely by providing a raft foundation provided the soft area is smaller than
the column spacing
one-third the column spacing
half the column spacing
three-fourth the column spacing
none of these.
Answer: Option B
The concrete slump recommended for beams and slabs ; is
25 to 50 mm
25 to 75 mm
30 to 125 mm
50 to 100 mm
none of these.
Answer: Option C

The entrained concrete is used in lining walls and roofs for making
heat insulated
sound insulated
neither (a) nor (b)
both (a) and (b).
Answer: Option D
For providing a raft foundation, the following activities are involved
  1. ramming the foundation bed
  2. excavation of the soil upto required depth
  3. laying the reinforcement over the foundation bed
  4. curing the cement concrete placed over reinforcement
  5. pouring the cement concrete over the reinforcement.

The correct sequence is
1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4
3, 2, 5, 1, 4.
Answer: Option C
During percussion drilling
ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole
caving or mixing of strata are caused in soft soils or cohesionless soils
the soil to a considerable depth below the bottom of the hole gets disturbed
all the above.
Answer: Option D
Raft foundation are generally preferred to when the area required for individual footing, is more than
25% to total area
30% of total area
40% to total area
50% of total area.
Answer: Option D
Pick up the incorrect statement from the following:
The retaining wall should be structurally capable to resist the applied earth pressure
The section of the retaining wall should be so proportioned that it may not overturn by the lateral pressure
The retaining wall should be safe against sliding
The foundation of the retaining wall should not be stressed beyond safe bearing capacity ; due to its weight and the force resulting from the earth pressure
to drain off water from the earth retained, weep holes are provided near the top of the retaining wall.
Answer: Option E
The process of keeping concrete moist for a certain period after its finishing, is known as
finishing of concrete
curing of concrete
placing of concrete
compaction of concrete
none of these.
Answer: Option B
Raft foundations are used for :
providing increased area of foundation over poor bearing capacity of soil
spanning over small soft or loose pockets
counter acting the hydrostatic effect
all the above.
Answer: Option D
The foundation which consists of a thick reinforced cement slab covering whole area to support heavy concentrated structural loads, is known as
combined footing
strap footing
raft footing
none of these
Answer: Option C

For a wall carrying heavy load on low bearing capacity soil,
lean concrete bed is provided
thick concrete bed is provided
reinforced concrete bed is provided
(a) and (c) of the above
(b) and (c) of the above.
Answer: Option D
The bearing capacity of a water logged soil, may be improved by
grouting
chemical action
drainage
compaction.
Answer: Option C
Two columns 50 cm x 50 cm and 60 cm x 60 cm carry 80 tonnes and 120 tonnes of loads respectively. The centre to centre distance between columns is 5.00 metres. The permissible bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following:
distance of C.G. of the loads from the smaller column = 3.00 m
the length of the foundation slab = 7.00 m
area of footing slab = 11.00 m2
width of the footing = 1.57 m.
all the above.
Answer: Option E

The formWork including the props can be removed from beams, only after
3 day
7 days
14 days
21 days.
Answer: Option C
The concrete slump recommended for foundations, is
25 to 50 mm
30 to 125 mm
50 to 100 mm
75 to 125 mm
none of these.
Answer: Option C


The construction joints in buildings are provided after
10 m
15 m
20 m
40 m
60 m.
Answer: Option D
Pick up the correct statements from the following :
cracks appear on the plastered surface in the form of hair cracks
in brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
excessive thermal variations in the backing or plaster causes the plaster to fall
all the above.
Answer: Option D
Pick up the correct statement from the following:
Plain cement concrete is equally strong in compression as well as in tension
Slump test is performed to check concrete strength
Curing of concrete is done for proper compaction of cement
Fineness modulus is the index number expressing the relative sizes of both coarse and fine aggregates
Concrete is a mixture of binding material, coarse aggregate and water.
Answer: Option D

Pick up the correct statement from the following :
Isolated footing is provided under column to transfer the load safely to soil bed
column footings may have steps or projections in the concrete base
heavily loaded column base must be provided steel reinforcement in both directions
the concrete offset should be at least 15 cm on all sides
all the above.
Answer: Option E
If h is the difference in level between end points separated by l, then the slope correction is . The second term may be neglected if the value of h in a 20 m distance is less than
m
1 m
2 m
3 m
Answer: Option D


The accuracy of measurement in chain surveying, does not depend upon
length of the offset
scale of the plotting
importance of the features
general layout of the chain lines.
Answer: Option D
Offsets are measured with an accuracy of 1 in 40. If the point on the paper from both sources of error (due to angular and measurement errors) is not to exceed 0.05 cm on a scale of 1 cm = 20 m, the maximum length of offset should be limited to
14.14
28.28 m
200 m
none of these.
Answer: Option B
Ranging in chain survey means
looking at an isolated point not on the line
establishing an intermediate point on the line
determining the distance between end points
determining the offset distance
none of these
Answer: Option B

The operation of resection involves the following steps
  1. rough orientation of the plane table
  2. the three lines form a triangle of error
  3. drawing lines back through the three control points
  4. select a point in the triangle of error such that each ray is equally rotated either clockwise or anti clockwise
  5. the points obtained by three rays is the correct location.
    The correct sequence is
1, 3, 2, 4, 5
1, 2, 3, 4, 5
1, 4, 3, 2, 5
1, 3, 2, 4, 5
Answer: Option A
If the length of a transition curve to be introduced between a straight and a circular curve of radius 500 m is 90 m, the maximum perpendicular offset for the transition curve, is
0.70 m
1.70 m
2.70 m
3.70 m
4.70 m
Answer: Option C
For quality control of Portland cement, the test essentially done is
setting time
soundness
tensile strength
consistency
all the above.
Answer: Option E
If 1500 g of water is required to have a cement paste 1875 g of normal consistency, the percentage of water is,
20%
25%
30%
35%
40%


Answer: Option B
Hydration of cement is due to chemical action of water with
Tricalcium silicate and dicalcium silicate
Dicalcium silicate and tricalcium aluminate
Tricalcium aluminate and tricalcium alumino ferrite
All the above.
Answer: Option D
Curing
reduces the shrinkage of concrete
preserves the properties of concrete
prevents the loss of water by evaporation
all of the above.
Answer: Option D
Curing a concrete for long period ensures better
volume stability
strength
water resistance
water tightness and durability
all the above.
Answer: Option E
Pick up the correct statement from the following:
Insufficient quantity of water makes the concrete mix harsh
Insufficient quantity of water makes the concrete unworkable
Excess quantity of water makes the concrete segregated
Excess quantity of water causes bleeding in concrete
All the above
Answer: Option E
Workability of concrete is measured by
Vicat apparatus test
Slump test
Minimum void method
Talbot Richard test.
Answer: Option B
Shrinkage in concrete can be reduced by using
low water cement ratio
less cement in the concrete
proper concrete mix
presaturated aggregates
all the above.
Answer: Option E
A construction joint is provided where
bending moment is small
shear force is small
the member is supported by other member
all the above.
Answer: Option D
Pick up the correct statement from the following:
According to the petrological characteristics, concrete aggregates are classified as heavy weight, normal weight and light weight
According to the shape of the particles, concrete aggregates are classified as rounded irregular, angular and flaky
According to the surface texture of the particles, the concrete aggregates are classified as glassy, smooth, granular, rough, crystalline, honey combed and porous
All the above.
Answer: Option D

Pick up the incorrect statement from the following:
The degree of grinding of cement, is called fineness
The process of changing cement paste into hard mass, is known as setting of cement
The phenomenon by virtue of which cement does not allow transmission of sound, is known as soundness of cement
The heat generated during chemical reaction of cement with water, is known as heat of hydration
None of these.
Answer: Option C

Permissible compressive strength of M 150 concrete grade is
100 kg/cm2
150 kg/cm2
200 kg/cm2
250 kg/cm2
300 kg/cm2
Answer: Option C
Slump test of concrete is a measure ofits
consistency
compressive strength
tensile strength
impact value.
Answer: Option A
Water cement ratio is
volume of water to that of cement
weight of water to that of cement
weight of concrete to that of water
volume of concrete to that of water
both (a) and (b) of the above.
Answer: Option E
Separation of water or water sand cement from a freshly concrete, is known
bleeding
creeping
segregation
flooding
none of these.
Answer: Option A
According to Water-Cement Ratio Law, the strength of workable plastic concrete
depends upon the amount of water used in the mix
does not depend upon the quality of cement mixed with aggregates
does not depend upon the quanity of cement mixed with aggregates
all the above
Answer: Option D
High temperature
increases the strength of concrete
decreases the strength of concrete
has no effect on the strength of concrete
none of these.
Answer: Option B
Allowable shear strength of concrete, depends upon
shear strength
tensile strength
compressive strength
none of these.
Answer: Option A
Workability of concrete mix with low water cement ratio is determined by
tensile strength test
slump test
compaction factor test
flexural strength test
none of these
Answer: Option C
While designing an air entrained concrete
water cement ratio is reduced
proportion of aggregates is reduced
an allowance for the entrained air is made
strength of the concrete, is reduced
all the above
Answer: Option E
Concrete gains strength due to
chemical reaction of cement with sand and coarse aggregates
evaporation of water from concrete
hydration of cement
All the above.
Answer: Option C
Expansion joints are provided if the length of concrete structures exceeds
10 m
15 m
15 m
35 m
45 m
Answer: Option E
Workability improved by adding
fly ash
hydrated lime
calcium chloride
bentonite
all the above.
Answer: Option E

If the slump of a concrete mix is 60 mm, its workability is
very low
low
medium
high
none of these.
Answer: Option C
Pick up the correct statement from the following:
Construction joints in columns are provided a few cm below the junction of beam
Construction joints in columns are provided at the bottom haunching
Construction joints in beams and slabs are provided within middel third
Constructionjoints are generally provided in positions subjected to least shear force
All the above.
Answer: Option E
The shortest distance between two places measured along the surface of the earth, is
length of the equator between their longitudes
length of the parallel between their longitudes
length of the arc of the great circle passing through them
none of these.
Answer: Option C
In the cantilever truss as shown in below figure, the horizontal component of the reaction at A, is
30 tonnes
60 tonnes
90 tonnes
120 tonnes
150 tonnes.
Answer: Option A
For a simply supported beam with a central load, the bending moment is
least at the centre
least at the supports
maximum at the supports
maximum at the centre.
Answer: Option D

A simply supported beam carrying a uniformly distributed load over its whole span, is propped at the centre of the span so that the beam is held to the level of the end supports. The reaction of the prop will be
half the distributed load
3/8th the distributed load
5/8th the distributed load
distributed load.
none of these.
Answer: Option C

The range within which a load can be applied on a rectangular column, to avoid any tensile stress, is
one-half of the base
one-fifth of the base
one-fourth of the base
one-fifth of the base
one sixth of the base on either side of centroid.
Answer: Option B
The shear stress at any section of a shaft is maximum
at the centre of the section
at a distance r/2 from the centre
at the top of the surface
at a distance 3/4 r from the centre
none of these.
Answer: Option C
The region of the cross-section of a column in which compressive load may be applied without producing any tensile stress, is known as the core of the cross-section. In circular columns the radius of the core, is
one-half of the radius
one-third of the radius
one-quarter of the radius
one-fifth of the radius
one-sixth of the radius.
Answer: Option C
The maximum bending moment due to a moving load on a simply supported beam, occurs
at the mid span
at the supports
under the load
anywhere on the beam
none of these.
Answer: Option C

A simply supported beam of span L carries a uniformly distributed load W. The maximum bending moment M is
Answer: Option C
A cantilever beam rectangular in cross-section is subjected to an isolated load at its free end. If the width of the beam is doubled, the deflection of the free end will be changed in the ratio of
8
1/8
1/2
2
3


Answer: Option C
When equal and opposite forces applied to a body, tend to elongate it, the stress so produced, is called
shear stress
compressive stress
tensile stress
transverse stress
Answer: Option C
Stress in a beam due to simple bending, is
directly proportional
inversely proportional
curvilinearly related
none of these.
Answer: Option A
The bending moment is maximum on a section where shearing force
is maximum
is minimum
is equal
changes sign.
Answer: Option D


A district road with a bituminous pavement has a horizontal curve of 1000 m for a design speed of 75 km ph. The super-elevation is
1 in 40
1 in 50
1 in 60
1 in 70
none of these.
Answer: Option A
The total length of a valley formed by two gradients - 3% and + 2% curve between the two tangent points to provide a rate of change of centrifugal acceleration 0.6 m/sec2, for a design speed 100 km ph, is
16.0 m
42.3 m
84.6 m
none of these
Answer: Option A
The advantage of providing superelevation on roads, is
higher speed of vehicles
increased volume of traffic
reduced maintenance cost of the roads
draining off rain water quickly
all the above.
Answer: Option E
For a vehicle moving with a speed of 80 km per hour, the brake reaction time, in ordinary cases, is
1 sec
1.5 sec
2.0 sec
2.5 sec
3.0 sec
Answer: Option D


 

Comments

Popular posts from this blog

mmup mechanical questions 06

mmup mechanical questions 1. Car chassis are: Felix, Rigid, stiff?    2. What is not a System parameter? Pressure, Temp, specific volume, Heat?                                    3. Reason for Fast track project?. Future material price, cost reduction?  4. Barometric gage? Atm,  atm & differential. Diff only? 5. Manometer? Differential, atm? 6. Centripole force? 7. Hooks law? 8. Onset plastic deformation? Yield, plastic, rigid 9. Stress and strain? Proportional 10. Forward plan. early start early finish 11.shahida work in inf mgm project, Run by inf mgm dept and helped through normal procedures by other dept. type of org? functional, projectized, .functional matrix....? 12.car dash board from? Polymer,metal? 13. Differential gear. Reducing speed, changing speed, jerk-o...

mmup mechanical questions 01

mmup mechanical questions 1- A material that makes deformation under sheer stress is : a. Liquid b. Gas c. Solid d. Fluid Answer :d. Fluid 2- To determine the type of turbulent flow in a rough vessel, you require: a. Reynolds number and relative roughness b. Relative roughness c. Mach number and Reynolds number d. Mach number and relative roughness Answer 3- If you have a cup of water at 70 degree Celsius and 1 Atmosphere, the liquid is: a. Saturated liquid b. Saturated vapor c. Condensate liquid d. None of the above Answer : Non of the above 4- Zero velocity of a flow inside a vessel will be: a. At the center b. At the periphery c. At the d. At the Answer 5- If you increase the water-cement ratio in the concrete: a. Concrete will lose its specifications b. Decrease the hardening time of concrete c. Decrease the slump d. Increase the slump Answer 6- If you were awarded a project, you wil...

mmup electrical questions 01

Electrical Questions MMUP Engineering 1)     The Manufacturing company gets material from 2 suppliers X & Y, Task Task Nodes Duration Procure material by X 2 Procure material by Y A 2 Delivery of Material from X B 7 Delivery of Material from Y B 11 Assembly and Completion C & D 2 If X delays the procurement of material by 2 days and company take 10 days to obtain the material, what shall be the delay(days) for product completion a.     0 b.     1 c.      2 d.     3 2)     If an alternator is over excited : a)     P.F is lagging. b)     P.F is leading c)     Is Unity d)     Is zero Rejection of Noise 3)     The input impedance of c...