1- Strategy considered to be under purview of senior management is:
A) Old school thinking
B) A new school of management thought
C) Necessary in a company structure
D) Beneficial to the Project Manager
E) Dependent on company goals

2- Project managers who do not understand the role that their project plays in accomplishing the organization's strategy tend to make all the following mistakes except:
A) Focusing on low priority problems
B) Overemphasizing technology as an end in and of itself
C) Focusing on the immediate customer
D) Trying to solve every customer issue
E) All the above are likely mistakes

3- Project selection criteria are typically classified as:
A) Financial and non-financial
B) Short-term and long-term
C) Strategic and tactical
D) Required and optional
E) Cost and schedule

4-The advent of project management has been most profound in
A) Automobile manufacturing
B) Construction
C) Information technology
D) The U.S. Department of Defense
E) Film making

5-Which of the following choices is not one of the stages of a project life cycle?
A) Conceptualizing
B) Defining
C) Planning
D) Executing
E) Delivering



6-In which of the following stages are you more likely to find status reports, many changes, and the creation of forecasts?
A) Conceptualizing
B) Defining
C) Planning
D) Executing
E) Delivering

7-Which of these is not part of the "technical dimension" of project management?
A) WBS
B) Budgets
C) Problem solving
D) Schedules
E) Status reports


8-From the list below, which is not a primary characteristic of organization culture?
A) Control
B) Team emphasis
C) History
D) Conflict tolerance
E) Risk tolerance

9-Who is responsible for determining how tasks will be done in a matrix project management structure?
A) The functional manager
B) The project manager
C) Both are responsible
D) This is no pattern of who takes responsibility
E) None of these are true

10-If you were awarded a project, you will start work:
a.    One week before the approval of the authorities
b.    After the approval of the authorities
c.     One day before the approval of the authorities

11-Project Scope Management:
d.    Define scope and control scope
e.    Executing scope and verify scope
f.      Closing process and Create work breakdown structure
g.    All of the above
h.    Only A & B

12-Scope Management starts with is:
i.      To identify the client requirements
j.      Meet the team
k.     Review strategic plan

13-Final as built drawings for what purpose
l.      To keep record for later maintenance
m.   To give more work to architect
n.    To be used for further renovation

14-Control department work starts
o.    From the beginning of the project
p.    During construction
q.    After construction

15-Project management is ideally suited except
r.     Accountability
s.     Flexibility
t.      Innovation
u.    Speed
v.     Repeatability


16-A critical path is the ----------------------in the project management:
w.    longest
x.     shortest
y.     none

17-The forward pass review of the project management will indicate the following:
z.     The earliest start of the task
aa.  The earliest finish of the task
bb.  Critical path (longest path)
cc.  Only A & B
dd.  All of the above

18-Intersecting point for WBS and OBS
ee.  Cost account
ff.    Intersect matrix
gg.  Project matrix
hh.  None of above

19-For operation and designed auto mobile factory
ii.     Mechanical Engineer
jj.     Civil Engineer
kk.  Chemical Engineer
ll.     Petroleum Engineer

20-Which of the following discipline is most suitable for doing a natural gas pipeline work?
mm.     Mechanical Engs
nn.  Petroleum Engs
oo.  Chemical Engs
pp.   Civil Engs

21-Gypsum board at residence and industrial building used  except
qq.  Low cost
rr.    Ease of installation
ss.  Recyclability

21-What is the last of estimation for project
tt.    Estimation
uu.  Assembly schedule

22-Which one of the following is suitable in engineering manner?   “Decision shall be based on reason than situation ’’.
vv.  Quantity Thinking.
ww.      Logical Thinking.
xx.  Interpersonal Skills.
yy.  Honesty.

23-What is QSAS?
zz.  Qatar Sustainability Assessment System

24-An activity in a project network can be represented by which of the following?
aaa.     Arrow
bbb.     Line
ccc.      Node
ddd.     All of the above
 
25-Before starting work at site, the major factor has to be checked is?
eee.     Access to site (EFE)
fff.   Storage of Water, tools & equipments
ggg.     Safety
hhh.     Approval from MMUP / Civil / Defense etc.
iii.    All of the above

26-Software programming flow
jjj.    Plan, Do, Check, Act
kkk.      Plan, Do, Act, Check
lll.    Plan, Act, Do, Check

27-First step of Scope planning starts with
mmm. Budgeting
nnn.     Current earning estimation
ooo.     Objectives and requirements to satisfy customer

28-In network which point getting more inward flow
ppp.     Float
qqq.     Critical path
rrr.  Slack
sss.      Merging point

29-What is the least level of WBS
ttt.   Deliverable
uuu.     Cost
vvv.      Work package
www.   Lowest sub deliverable

Comments

Popular posts from this blog

mmup mechanical questions 06

mmup mechanical questions 1. Car chassis are: Felix, Rigid, stiff?    2. What is not a System parameter? Pressure, Temp, specific volume, Heat?                                    3. Reason for Fast track project?. Future material price, cost reduction?  4. Barometric gage? Atm,  atm & differential. Diff only? 5. Manometer? Differential, atm? 6. Centripole force? 7. Hooks law? 8. Onset plastic deformation? Yield, plastic, rigid 9. Stress and strain? Proportional 10. Forward plan. early start early finish 11.shahida work in inf mgm project, Run by inf mgm dept and helped through normal procedures by other dept. type of org? functional, projectized, .functional matrix....? 12.car dash board from? Polymer,metal? 13. Differential gear. Reducing speed, changing speed, jerk-o...

mmup mechanical questions 01

mmup mechanical questions 1- A material that makes deformation under sheer stress is : a. Liquid b. Gas c. Solid d. Fluid Answer :d. Fluid 2- To determine the type of turbulent flow in a rough vessel, you require: a. Reynolds number and relative roughness b. Relative roughness c. Mach number and Reynolds number d. Mach number and relative roughness Answer 3- If you have a cup of water at 70 degree Celsius and 1 Atmosphere, the liquid is: a. Saturated liquid b. Saturated vapor c. Condensate liquid d. None of the above Answer : Non of the above 4- Zero velocity of a flow inside a vessel will be: a. At the center b. At the periphery c. At the d. At the Answer 5- If you increase the water-cement ratio in the concrete: a. Concrete will lose its specifications b. Decrease the hardening time of concrete c. Decrease the slump d. Increase the slump Answer 6- If you were awarded a project, you wil...

mmup electrical questions 01

Electrical Questions MMUP Engineering 1)     The Manufacturing company gets material from 2 suppliers X & Y, Task Task Nodes Duration Procure material by X 2 Procure material by Y A 2 Delivery of Material from X B 7 Delivery of Material from Y B 11 Assembly and Completion C & D 2 If X delays the procurement of material by 2 days and company take 10 days to obtain the material, what shall be the delay(days) for product completion a.     0 b.     1 c.      2 d.     3 2)     If an alternator is over excited : a)     P.F is lagging. b)     P.F is leading c)     Is Unity d)     Is zero Rejection of Noise 3)     The input impedance of c...